|
<<Forestry>>
<<Land
& Water Management>>
<<Agriculture>>
<<RF
Management>>
<<R
& D Programmes
>>
Watershed
Management
From mid-eighties, development of dry land agriculture on
watershed basis has been a national strategy for sustained
productivity and rational utilization of natural resources.
The total resource can be properly developed only by adopting watershed approach.
In terms of resource development, it covers development and
management of resources like soil, water, vegetation and all
associated components. It essentially relates to soil and
water conservation in the watershed which includes proper land
use, protection of land against all forms of degradation,
building and maintaining soil fertility, water conservation
and harvesting, proper management of surface and ground water,
flood protection, sediment reduction, increasing productivity
from land uses etc.
Watershed development is an important approach to improve
the social and economic conditions of people living in
resource poor, rainfed areas, covering approximately
two-thirds of the country’s agricultural land. In addition to
achieving biophysical objectives, contemporary watershed aims
to promote the rural livelihoods of people, especially the
poor and disadvantaged.
|
Watershed Projects in Khedbrahma
Taluka,
Sabarkantha District |
|
Sembaliya - Dantiya Watershed
Project
|
|
Total geographical area of 7
Villages |
4090.8 Hectares |
|
Watershed Area |
1705 Hectares |
|
Total Households in Watershed
Area |
1099 |
|
Total Population in
Watershed Area |
6765 |
|
Total Households of 7
Villages |
2008 |
|
Total Population of 7
Villages |
12363 |
VIKSAT initiated watershed based interventions in Sembaliya
and Dantiya tribal dominated villages in Khedbrahma taluka of
Sabarkantha district since February 2005. The patient and
consistent efforts resulted in successful ‘Four Days Mandatory
Shramdaan’ by the community only in December 2005.
By March 2006, Watershed Development Committee, a people’s
institution, comprising of village representatives as per
NABARD guidelines was formed to implement the watershed
project under VIKSAT guidance and support. This lead to
approval of ‘Capacity Building Phase (CBP)’ by NABARD under
Watershed Development Fund (WDF) covering 99.17 Hectares
of land in April 2006. The watershed project measures such as
construction of Earthen bunds, Stone outlets, Stone bunds,
Stone gully plugs and tree plantation were carried out during
the year 2006 with the release of first installment of grant
by NABARD in June 2006.
Feasibility
Study Report
In September 2007, an application was made to WDF, NABARD
to issue an approval to conduct feasibility survey of the
entire watershed area of 1705 Hectares of land for the purpose
of Full Implementation Phase (FIP). NABARD sanctioned the
grant of Rs. 1,76,231/- for FSR by the first week of March
2008.
VIKSAT has completed the survey and submitted FSR in the
second week of December2008. The total proposed cost of the
project, as per FSR, is Rs. 16,616,773/- and the
project period is 4 years.
Interim
Phase (IP)
However, considering the time the sanction of FIP may take,
it was decided to submit a proposal for Interim Phase for
89.59 Hectares in Ambasar and Umbarva villages of the project
area with a total project cost of Rs. 14,69,508 with a dual
purpose. One was to maintain the continuity of the project so
that momentum achieved during the implementation of CBP is
maintained. But, another important aspect was to provide work
and livelihood options to the people as the entire project
area witnessed much lower rainfall (Only 389 mm as measured at
VIKSAT Field Office, Kheroj) during the last monsoon and the
prevailing drought like conditions. Further, the
implementation of project measures before next monsoon could
be extremely useful in soil and water conservation in these
two villages that may lead to improved water availability for
irrigation during the next year.
Latest
Status of the project
-
Documents
with request letter have been submitted in the last week of
February 2009 to get sanction for the grant for Interim Phase.
-
CBP is
completed in February, 2009 and closure report has been
submitted.
-
Sanction
for IP is awaited.
-
Final
Feasibility Study Report after field visit by NABARD
verification visit on 17th & 18th February, 2009 has been submitted for getting sanction for Full Implementation Phase.
The NABARD team has made following observation after the
verification visit.
“The
effort taken by your staff in implementation of the watershed
programme is commendable”. (Letter Ref No. NB.RO.GUJ/12687/WDF/WSDC-54/2008-09
dated 25 February 2009)
|
Navamota Watershed Project |
|
Total Village Area of 7 Villages |
1956.7 Hectares |
|
Watershed Area |
990 Hectares |
|
Total Households in Watershed
Area |
652 |
| Total
Population in Watershed Area |
4564 |
| Total
Households of 7 Villages |
1285 |
| Total
Population of 7 Villages |
8313 |
VIKSAT also initiated watershed
based interventions in Navamota and surrounding other six
tribal dominated villages, namely Mahudi, Umbora, Bubadiya na
Chhapra, Tebda and Tebdi having total geographical area of
1956.7 Ha in Khedbrahma taluka of Sabarkantha district by
submitting watershed information sheet in January 2007 to Indo
German Watershed Development Programme (IGWDP) - NABARD. After
receiving positive reply from IGWDP, VIKSAT submitted final
proposal for watershed development in the month of July 2007.
The total watershed area is 990.58 Hectares.
The project is being implemented
by ‘Navamota Juth Jalstrav Vistar Vikas Mandal’ a community
organization formed with the facilitation and management by
VIKSAT for the purpose of implementation of Watershed
Programme.
IGWDP sanctioned Pre-Capacity
Building Phase (Pre-CBP) in December 2007. Shramdaan was
completed in February 2008 and CBP proposal was submitted in
the first week of July, 2008 which was sanctioned in September
2008 and 1st installment was received in November
2008. To make people aware of watershed project in their area
and to seek their active and meaningful participation in the
programme, CBP launching ceremony was arranged. The ceremony
was chaired by Taluka Development Officer Shri S.M. Patel. The
other dignitaries who attended and addressed the gathering
were PMU – IGWDP, Dahod in Charge Dr. D.V. Deshpande, NABARD
DDM-Himmatnagar Shri Sharad Ahire, Shri Khurshid Alam,
Consultant-IGWDP, Shri Dhimon – Lead Bank Manager – Dena Bank,
Dr. H.B.Patel, APO from Integrated Tribal Development Project
Office and Shri S.M.Ninama – RFO Extension Range. Navamota
Primary School Principal Shri Bachubhai Parmar also attended
the ceremony along with members of VWC members and nearly 500
villagers from the project area villages. It is interesting to
note that half of the gathering was women from the project
area.
Then after, a Gramsabha was
organized on 4th December 2008 at the village
‘Bubadiya na Chhapra’ inviting the villagers of CBP area
villages namely Kheroj, Bubadiya na Chhapra, Navamota and
Umbora to inform and explain the community about IGWDP
supported watershed programme and its advantages.
The series of programme helped
to create very good understanding of the watershed programme
which helped to give momentum to the implementation of CBP.
The village community of Umbora village speedily implemented
their part of programme by constructing farm bund, stone bund,
gully plug, stone outlet etc and they even received the
payments also for the same as per NABARD norms.
To motivate the farmers of other
three villages to implement watershed works, under CBP, in
their farms as fast as possible, an exposure cum training
programme at Umbora village was organized on 11th
February 2009 in which 42 male and 9 women participated.
The training covered following
topics:
-
Meaning and Importance of Watershed
Programme
-
NABARD watershed programme
implementation policy and spirit behind it
-
Role of village community, Jalstrav
Vistar Vikas Samiti, VIKSAT and IGWDP(NABARD)
-
Explanation of activities that can be
implemented under the programme and care required to be
exercised;
The participants saw the works
carried out by Umbora farmers in their fields and discussed
their experience which helped to achieve the purpose of the
programme.
At the
end of the programme, participants seemed to be fully
satisfied as they gave whole-hearted assurance to complete
their field work as early as possible and without any delay
for any reasons.
Present status of CBP
Though, 1st installment for CBP
implementation was released in the last week of October 2008,
the project implementation in the fields could be started only
in the month of February 2009 as fields were having standing
crops. But, once the fields were open, the implementation work
started with great zeal among the villagers for two reasons.
One of them being lack of irrigation facility for Rabi crop
due to scanty rainfall, only 389 mm as measured at VIKSAT
Kheroj office, far less than normal annual rainfall, leaving
people without any agriculture farm activities. In such
circumstances, the best option for the people was to work on
development of watershed structures in their fields and earn
labour wages out of it. Second reason was trust and faith
developed among VIKSAT staff and villagers due to rapport
developed as a consequence of series of programme conducted by
VIKSAT in the project area such as Pre-CBP activities, Cattle
Camp and Human medical check-up and treatment camp, CBP
launching ceremony and exposure visit to other areas where
watershed programme has been implemented and people have been
grossly benefited.
This all helped in the speedy
implementation of CBP. By 20th March, 2009 more
than 60% grant fund was utilized, meeting the condition to
claim the next installment.
***
|